CS H2- Project Plan
MedTrainer CS H2 Plan: Moving from Generic to Specialized CSM Team
- 1 Strategy
- 2 Objectives
- 3 Phase 1: Tactical Adjustments (June - July)
- 4 Phase 2: Communicate the Plan and Execute Initial Actions (August)
- 5 Phase 3: Standardization and First Contact (September - October)
- 6 Phase 4: Optimization and First Insights (November)
- 7 Phase 5: Finish Strong (December)
- 8 Key Metrics
- 9 Other Metrics
- 10 Dashboard Metrics (to be included in relevant phases)
Strategy
Our strategy for the second half of the year centers on transitioning from a generic Customer Success Manager (CSM) approach to a specialized one. By segmenting our customer base and aligning specific CSMs to each segment (Strategic, Core, and Digital customers), we aim to provide more focused and effective customer engagement. This specialized approach will enable us to better address the unique needs of each customer segment, improve overall customer satisfaction, and enhance the value realization for our customers.
Strategic customers are defined as: MRR >$3,500
Core customers are defined as: all customers not falling into the categories of MRR $0-$500, Employee Count 0-50 or MRR >$3,500 (all customers who are not Digital or Strategic)
Digital customers are defined as: MRR $0-$500 and Employee Count 0-50.
Objectives
See: Key Metrics for targets for all objectives.
Better Engagement: Develop tailored engagement models to foster deeper relationships and improve communication with customers.
Clear Expectations for CSMs: Define and communicate clear roles and responsibilities for CSMs based on customer segments to drive accountability and ownership.
Better Retention: Implement targeted strategies to reduce churn and improve customer retention rates.
Maintaining Upsells/Expansions: Establish and achieve upsell and expansion targets to drive revenue growth.
Increase References: Enhance customer advocacy by increasing the number of referenceable customers.
Phase 1: Tactical Adjustments (June - July)
Initiatives:
General Ops
Conduct Additional Churn Analysis - Complete (2024 churn to date 1 july.xlsx) 🟢
Wrap Legacy Ops Projects
Specialization
Categorize Customers - Complete (2024-06-27 Company Segment Analysis May24) 🟢
Finalize Engagement Models - Complete (Digital Customer CS Plan, Core Customer CS Plan, Strategic Customer CS Plan) 🟢
Identify CSMs for Each Segment 🟢
Establish Initial Victory Plan for H2 - Complete (MT CS Victory Plan Q3 24 v. 1.1) 🟢
Set Upsell/Expansion Targets 🟢
Milestones:
June 20 - June 30 🟢
Complete churn analysis and identify top 100 customers by MRR.
June 26 🟢
Set upsell and expansion targets for Q3.
July 1 🟢
Initial victory plan for Q3 completed and communicated.
July 15
Categorize all customers into Strategic, Core, and Digital segments. 🟢
Finalize engagement models for each segment. 🟢
Complete the assignment of CSMs to each segment. 🟢
Standardize churn data collection processes. 🟢
Success Milestones:
Churn Analysis Completion
Target: 100% by June 30. 🟢
Customer Segmentation
Target: 100% by July 15. 🟢
Engagement Model Finalization
Target: 100% by July 15. 🟢
Standardized Data Collection
Target: 100% by July 15. 🟢
CSM Assignment
Target: 100% by July 15. 🟢
Initial Victory Plan Completion
Target: Completed and communicated by July 1. 🟢
Upsell/Expansion Targets
Target: Set by June 26. 🟢
Phase 2: Communicate the Plan and Execute Initial Actions (August)
Initiatives:
Communicate Changes to the Team 🟢Â
Train CSMs by Segment 🟡
Launch Pilot Programs 🟡
Collect Initial Feedback 🟡
Establish NPS Program 🟡
Milestones:
August 5
Complete team meetings to explain new structure and models. 🟢
August 15
Complete training of CSMs on engagement models and risk management strategies. 🟡
Launch pilot programs with selected accounts.🟡
August 31
Collect initial feedback from at least 50% of pilot accounts. 🟡
Establish and launch the NPS program. 🟡
Success Milestones:
Team Communication
Target: 100% by August 5. 🟢
CSM Training Completion
Target: 100% by August 15. 🟡
Pilot Program Launch
Target: Launch by August 15.🟡
Initial Feedback Collection
Target: Feedback from at least 50% of pilot accounts by August 31. 🟡
NPS Program Establishment
Target: Program live by August 31.🟡
Â
Phase 3: Standardization and First Contact (September - October)
Initiatives:
Standardize Best Practices and Models
Update Playbooks and Training Processes
Increase Data Collection
Enhance Engagement Frequency
Establish Executive Sponsorship Program
Create Dashboards
Milestones:
September 30
Document and standardize successful practices.
Set up Customer Advisory Panel (CAP) and gather feedback.
Launch Executive Sponsorship Program.
October 15
Update playbooks and complete additional training.
October 31
Increase data collection by 25%.
Increase engagement frequency by 20%.
Create and implement key dashboards.
Success Milestones:
Standardization Completion
Target: 100% by September 30.
Playbook and Training Updates
Target: 100% by October 15.
Increased Data Collection
Target: 25% increase in data points collected by October 31.
Engagement Frequency
Target: 20% increase by October 31.
Executive Sponsorship Program Establishment
Target: Program live by October 31.
Dashboard Establishment
Target: Dashboards live by October 31.
Â
Phase 4: Optimization and First Insights (November)
Initiatives:
Optimize Data Collection Processes
Establish Velocity Score
Ensure Adherence to Standardized Practices
Collect Customer Feedback
Milestones:
November 15
Implement advanced data collection and analysis tools.
November 30
Develop and launch a velocity score tracking system.
Ensure 100% adherence to standardized practices.
Collect feedback from at least 75% of customers.
Success Milestones:
Optimized Data Collection
Target: 100% by November 15.
Velocity Score Establishment
Target: System live by November 30.
Standardized Practices
Target: 100% adherence by November 30.
Customer Feedback Collection
Target: Feedback from at least 75% of customers by November 30.
Â
Phase 5: Finish Strong (December)
Initiatives:
Review Engagement Models
Confirm Active Management of Segments
Review ARR/NRR Progress
Establish Next Victory Plan
Milestones:
December 15
Complete review of engagement models.
Ensure all customer segments are actively managed by their assigned CSMs.
December 20
Analyze and review ARR/NRR progress.
December 31
Develop and approve the next victory plan for the following year.
Success Metrics:
Engagement Model Review
Target: 100% review completion by December 15.
Active Management Confirmation
Target: 100% by December 15.
ARR/NRR Progress Review
Target: Review and report completion by December 20.
Next Victory Plan Establishment
Target: Plan completed and approved by December 31.
Â
Â
Key Metrics
Objective 1: Better Engagement
Metrics:
Engagement Rate:
Strategic Customers: Achieve a 50% engagement rate within 6 months.
Core Customers: Achieve a 40% engagement rate within 6 months.
Digital Customers: Achieve a 30% engagement rate within 6 months.
Measurement: Track the percentage of customers interacting with communications (emails, meetings, webinars).
Content Consumption:
Target: Increase content consumption by 50% within 6 months.
Measurement: Measure the number of times customers access and interact with educational content (videos, articles, webinars).
Objective 2: Clear Expectations for CSMs
Metrics:
CSM Training Completion:
Target: 100% of CSMs trained on new engagement models by August 15.
Measurement: Completion rate of training sessions and feedback quality.
Role Clarity:
Target: Define and communicate clear roles and responsibilities for CSMs by July 31.
Measurement: CSMs’ understanding and execution of their roles, measured through performance reviews.
Objective 3: Better Retention
Metrics:
Churn Rate:
Strategic Customers: Reduce churn rate from 8% to 5% within 12 months.
Core Customers: Reduce churn rate from 10% to 7% within 12 months.
Digital Customers: Reduce churn rate from 12% to 9% within 12 months.
Measurement: Track the percentage of customers discontinuing their subscriptions or services.
Customer Retention Rate:
Target: Achieve a retention rate of 90% within 12 months.
Measurement: Measure the percentage of customers retained over a specific period.
Objective 4: Maintaining Upsells/Expansions
Metrics:
Upsell and Cross-sell Rates:
Target: Achieve a 15% upsell/cross-sell rate within 12 months.
Measurement: Track the rate at which customers purchase additional products or services.
Expansion and Upsell Targets:
Target: Set by June 26.
Measurement: Track the achievement of upsell and expansion targets.
Objective 5: Increase References
Metrics:
Referenceable Customers:
Target: Increase the number of referenceable customers by 20% by the end of Q3.
Measurement: Number of customers willing to provide testimonials, case studies, or serve as references.
Other Metrics
Customer Satisfaction (CSAT) and Net Promoter Score (NPS)
Metrics:
CSAT:
Strategic Customers: Achieve an average CSAT score of 90% or higher within 6 months.
Core Customers: Achieve an average CSAT score of 87% or higher within 6 months.
Digital Customers: Achieve an average CSAT score of 85% or higher within 6 months.
Measurement: Collect CSAT scores through surveys after key interactions (onboarding, support resolution, QBRs).
NPS:
Target: Increase NPS from +30 to +40 within 12 months.
Measurement: Measure customer loyalty and likelihood to recommend your product to others.
Onboarding Efficiency
Metrics:
Onboarding Completion Rate:
Strategic Customers: Achieve a 95% onboarding completion rate within 30 days.
Core Customers: Achieve a 90% onboarding completion rate within 30 days.
Digital Customers: Achieve a 70% onboarding completion rate within 30 days.
Measurement: Track the percentage of new customers who complete the onboarding process.
Time to First Value (TTFV):
Target: Reduce TTFV by 20% within 6 months.
Measurement: Measure the average time for new customers to achieve their first significant value from MedTrainer.
Operational Excellence
Metrics:
Standardized Practices:
Target: 100% adherence to standardized practices by November 30.
Measurement: Monitor compliance and effectiveness of standardized practices.
Digital Tools Implementation:
Target: Implement necessary digital systems and processes by September 30.
Measurement: Track the implementation and utilization of digital tools.
Employee Engagement and Development
Metrics:
Training and Growth:
Target: 100% of the CS TEAM has 1-3 growth areas with mutual review every 90 days.
Measurement: Track training completion and performance improvements based on feedback.
Recognition Program:
Target: Develop and launch recognition program by September 30.
Measurement: Track the frequency and impact of recognition on employee performance and satisfaction.
Dashboard Metrics (to be included in relevant phases)
Engagement Dashboard
Metrics: Engagement rate, content consumption, frequency of touchpoints.
Target: Dashboard live by MONTH/DAY.
Health Score Dashboard
Metrics: Health scores, changes in health scores over time, correlation with churn.
Target: Dashboard live by MONTH/DAY.
Churn Rate Dashboard
Metrics: Monthly churn rate, reasons for churn, proactive saves.
Target: Dashboard live by MONTH/DAY.
Upsell/Expansion Dashboard
Metrics: Upsell and expansion opportunities, conversion rates, pipeline growth.
Target: Dashboard live by MONTH/DAY.